Pakistan

NHA completed 33 road projects at 13% increased cost since 2008

NHA projects

National Highway Authority (NHA) successfully completed 33 projects at increased cost, which was nearly 13 percent more than the initial bid in 2008. 

This was unveiled before the sub-Committee on the Senate Standing Committee on Communications held to find causes for cost overruns only of completed/ongoing projects of the NHA from 2008 with a minimum overall cost of not less than one billion rupees. 

The meeting was held under the Convenorship of Senator Saifullah Abro. Senator Danesh Kumar and Senior Officers from the Ministry of Communications were also present. 

The sub-Committee reviewed different accomplished and current projects by the National Highway Authority (NHA) from 2008 onwards, to find out cost overruns and the reasons for them. 

The Committee was apprised that 33 projects were completed but at an increased cost, which was around 13 percent more than the initial bid. 

Read more: NHA mobilised to rehabilitate road links devastated by floods

Informing the parliamentary panel, NHA officials stated the main reasons for increased costs of projects which included the difference between financial funds and financial phasing in PC-I; cost escalation; additional scope of work and land acquisition issues. 

Moreover, the Committee also reviewed the Lakhi- Naudero – Larkana project, Larkana – Khairpur Bridge Project, Zhob – Mughal Kot Project, and the Larkana – Moenjo Daro Road Project. The Hyderabad – Sukkur Road project was also under discussion, sources added. 

The Committee expressed displeasure with regard to the submitted data and ordered the Ministry to provide a comprehensive summary of the prequalification and bidding process. 

Senator Saifullah Abro highlighted the need for the prequalification process to be transparent and for bids to be awarded on merit. He had the opinion that following international standards in this regard would be beneficial. 

Giving the details of the projects from 2008, the NHA officials had earlier told the committee that there were a total of 125 projects. Afterward, other details were submitted in light of the committee’s questionnaire. 

Furthermore, projects were given to different companies of the same contractor while big and reputed companies were deliberately disqualified, the committee convener stated. 

Most Popular

To Top